NEW STAIR TREADS

Last October first week we ordered new “Stair Treads” to replace stairs, these thread matts is over 40 years of use and wear, tear, and its time to replace them.…

NORTH FACE RENOVATIONS

Happy New Year!! Great news to share from the Renovation/Elevator Project (REP) for Thompson Hall. Minnesota Historical Society awarded the Deaf Club another grant for $215,000 to focus on the…

PHASE 2 COMPLETED

Excellent news! Phase two of the Renovation/Elevator Project is now complete with the construction documents for the building We were able to do this with the Minnesota Historical Society Legacy…

BATHROOM FEATURES

Did you know that the Thompson Hall Renovation/Elevator Project (REP) includes plans to update the bathrooms in the lower level (see photo for the tiles for the walls, white square…

90% REVIEW REPORT

90% completed review report of Design Schematics and Construction Documents May 4, 2021 Charles Thompson Memorial Hall – 90% Design Development Submission – 04-29-2021 – Specifications Charles Thompson Memorial Hall…

60% REVIEW REPORT

60% completed review report of Design Schematics and Construction Documents CTMH – 60% Design Development Submission – 01-29-2021 – Arch Specs CTMH – 60% Design Development Submission – 01-29-2021 –…

30% REVIEW REPORT

30% completed review report of Design Schematics and Construction Documents Herman Fuechtmann speaking: Hi! I want to give you an update from the Renovation and Elevator Project Committee. Last November…

BREAKDOWN OF PHASES

Phase one for accessibility design and HSR is completed. We spent $35,427.22 on that. Funding sources for that were $17,000 saved up from prior elevator fundraising in late 1990s early…