Front Stair Renovation Project Update
Front Stair Renovation Project Update…the project is 60% completed, but was put on hold due to waiting for materials and availability of the builders. Great news! The builders will start
Front Stair Renovation Project Update…the project is 60% completed, but was put on hold due to waiting for materials and availability of the builders. Great news! The builders will start
Update June 26, 2023 from Architect Todd Grover from MacDonald and Mack Architects: There are balusters, columns, and railings now in the trailer in Thompson Hall’s front yard! They were
CTMH’s Porch Restoration was started on December 20, 2022 The reason for work starting in wintertime is that many builders and companies are already booked or have a
Update as on 8-3-2022 on Charles Thompson Memorial Hall’s North (Front) Porch Renovations: Abbreviations Key: Charles Thompson Hall (CTH) Renovations and Elevator Project (REP) MacDonald and Mack Architects (MMA)
We raised $532,000 so far and have enough money to start working on restoring the front porch this summer! We need approximately $1,700,000 to build the addition and the elevator
Deaf Equity is hosting a Project Spotlight Zoom Event for Charles Thompson Hall Renovation/Elevator Project. Join us to learn about the project, updates, how you can support, what’s next
Last October first week we ordered new “Stair Treads” to replace stairs, these thread matts is over 40 years of use and wear, tear, and its time to replace
Happy New Year!! Great news to share from the Renovation/Elevator Project (REP) for Thompson Hall. Minnesota Historical Society awarded the Deaf Club another grant for $215,000 to focus on the
Excellent news! Phase two of the Renovation/Elevator Project is now complete with the construction documents for the building We were able to do this with the Minnesota Historical Society Legacy